Vertex Steel Detailing supports general contractors' steel scopes with submittal packages, erection drawings, RFI drafting and SDS/2 model exports for coordination, prepared in accordance with AISC 303 and AISC 360. Detailing usually runs through your steel fabricator, so the team works inside that contractual chain and keeps the submittal schedule visible from intake to fabrication release.
How does steel detailing fit into a general contractor's schedule?
Steel detailing sits on the critical path between subcontract award and steel arriving on site. Shop drawings must be detailed, reviewed and approved before fabrication starts, and fabrication must finish before erection. A detailing delay or a slow approval cycle moves every date after it, which is why the steel submittal deserves tracking from the day the package is sent.
| Stage | Usually owned by | What the general contractor tracks |
|---|---|---|
| Detailing and internal check | Detailer, for the fabricator | Submittal date and open RFIs |
| Approval review | Engineer of Record and architect | Review duration and comment volume |
| Comment incorporation | Detailer | Resubmittal or release date |
| Fabrication | Fabricator | Shop start and delivery dates |
| Erection | Erector | Erection sequence and site readiness |
On Vertex's published reference project, the package went from Rev A for approval on September 3, 2026, to Rev 0 for fabrication on September 9, 2026. That included review time and was one package, so treat it as a data point rather than a planning figure.
Who contracts for steel detailing on a typical project?
On a typical US project the steel fabricator is responsible for shop and erection drawings under AISC 303, and the fabricator either details in-house or engages a detailer. The general contractor holds the fabricator's subcontract and manages the submittal, not the detailer directly. Vertex works within whichever chain your contracts set up.
That chain matters for RFIs and approvals: questions and submittals flow from detailer to fabricator to general contractor to the design team, and answers flow back. If you are arranging steel detailing yourself, for example on a misc metals scope or before a fabricator is selected, confirm at intake who holds responsibility for the drawings under your contracts.
How are steel submittals prepared and tracked?
Steel submittals are organized by specification section, issued with a transmittal that lists every sheet and its revision, and tracked from the approval issue to the fabrication release. On the reference project, the approval issue was Rev A and the fabrication issue Rev 0, so anyone reading a sheet could tell whether it was cleared to build.
| Submittal item | What it contains |
|---|---|
| Transmittal | Sheet list, revision of each sheet, issue purpose |
| Erection drawings | Plans, elevations and sections with piece marks |
| Shop drawings | Assembly and part details with bills of material |
| Bolt lists | Field bolts by connection for purchasing and installation |
| RFI log | Open and answered questions affecting the submittal |
Before any submittal is issued, every drawing is checked by a second person who did not draw it. The sequence is on the quality control page.
How are RFIs handled on the steel scope?
Vertex drafts steel RFIs with sheet, grid and detail references and sends them through the contractual chain to the Engineer of Record or architect. Each RFI is logged with its status. Pieces affected by an open question are held or flagged on the drawings, so detailing continues elsewhere without building on assumptions.
The team works in India, 9 hours 30 minutes ahead of US Eastern Daylight Time, so an answer that reaches the team at the end of the US day is typically worked into the model during the US night. The RFI log gives you a factual view of which questions are holding the submittal and who they are waiting on.
How does the steel model support coordination with other trades?
The SDS/2 model covers the steel, and clash review inside SDS/2 catches steel-to-steel conflicts before drawings are issued. Coordination with mechanical, electrical, plumbing and architectural models happens in the project team's own coordination process, using an IFC export of the steel model. Conflicts found there come back to detailing as RFIs or changes.
Being clear about that split avoids a common assumption: a detailer's clash review is not a multi-trade coordination review. If your project runs model coordination meetings, ask for the IFC export at intake and agree how often it is refreshed as the steel model develops.
What do erection drawings give the field team?
Erection drawings give the erector and your site team the plans, elevations and sections that show where every piece mark goes, with field connection details and field bolt lists. Where they are in scope, anchor rod setting plans and embed layouts come first, because concrete work depends on them. Site logistics and the erection sequence build on these sheets.
Piece marks on the erection drawings match the ship marks on the shop drawings and on the pieces delivered to site, so the crew can find and set each member without guessing. See erection drawings for what each sheet contains.
How is miscellaneous steel handled on a general contractor's project?
Miscellaneous steel, such as stairs, handrails, ladders, embeds and canopies, is often a separate specification section and sometimes a separate subcontract. Its biggest schedule risk for a general contractor is embeds: they must be detailed, approved and delivered before the concrete pours they are cast into, so they are released ahead of the rest of the misc steel.
Stairs and rails depend on floor-to-floor heights and slab edges built by other trades, so their drawings carry field-verify notes where conditions are not yet built. See miscellaneous steel detailing for how each item is detailed.
What does steel detailing cost, and who pays for it?
Vertex charges $15–20 USD per hour, varying with connection complexity, miscellaneous steel density, revision volume and turnaround pressure. Who pays depends on your contracts: in most cases detailing is part of the fabricator's price, and the general contractor pays for it through the steel subcontract rather than directly. Design changes that add detailing hours usually flow through change orders.
The steel detailing rates page explains what moves a package within the range and how detailing is commonly quoted. How a package moves from documents to fabrication release is on the process page, and structural steel detailing covers the full scope of a primary framing package.
Frequently asked questions
Can steel detailing be accelerated when the submittal is behind schedule?
Sometimes. A compressed schedule needs complete documents, fast RFI answers and a phased release, and turnaround pressure moves the hourly rate toward $20. Review cycles by the design team still have to fit inside the schedule.
Can you provide an IFC model for coordination?
The SDS/2 steel model can be exported to IFC for the project's coordination process. Ask for it at intake and agree how often it should be refreshed as detailing progresses.
Who reviews and approves the steel shop drawings?
The Engineer of Record and architect, as your contract and AISC 303 set out. Vertex checks every drawing before it is submitted, but the approval review stays with the design team.
Do you prepare anchor rod and embed layouts?
Yes, when they are in the package scope. Anchor rod setting plans and embed layouts are usually released first, because concrete work depends on them.
Keep reading
Related pages
- Erection drawingsErection plans, elevations, sections and field bolt lists that show the field crew where every piece mark goes.
- Steel detailing processHow a steel package moves from contract drawings to fabrication release, with the inputs and outputs at each stage.
- Quality controlThe checking sequence every package moves through: model review, clash checks, independent drawing checks and revision control.
- Steel detailing ratesPublished steel detailing rates: $15–20 per hour, what moves a project within that range, and how packages are quoted.
Start a package
Send the drawings. We'll map the path to fabrication.
Share contract drawings, specifications, your shop standards and target dates. We review the package, send back scope questions, and quote hours against the published $15–20 per hour range.